Preparation of stage 2 shotcrete basement walls are in progress with concrete pour in a couple days. There’s another 1.5 meters to dig to get to the underside of the basement 2 slab, plus a further 2.0 meters for the car stacker pit. The project team has set its target to complete all basement excavation, footings and drainage before the Christmas break.